multiple PD/PI, multiple program director, multiple principal investigator, post award
9.5 Post-Award Administration
If multiple PD/PIs are from multiple organizations, NIH will issue the award to the applicant organization which will administer the award using consortium or subaward arrangements in accord with the Consortium Agreements chapter. Budgets, including F&A costs Necessary costs incurred by a recipient for a common or joint purpose benefitting more than one cost objective, and not readily assignable to the cost objectives specifically benefitted, without effort disproportionate to the results achieved. To facilitate equitable distribution of indirect expenses to the cost objectives served, it may be necessary to establish a number of pools of F&A (indirect) costs. F&A (indirect) cost pools must be distributed to benefitted cost objectives on bases that will produce an equitable result in consideration of relative benefits derived. associated with subawards, will be determined according to existing policy. Changes in the allocation and the size of subawards will be handled in the same way as single PD/PI awards.
Responsibility for all required reports is shared by the PD/PIs and the recipient institution. Only one of each required report should be submitted. Although all PD/PIs are responsible for the content of all reports, only one PD/PI should upload information in the eRA Commons. As with most other Commons features, only the recipient Signing Official may submit the reports to NIH, including closeout reports (final invention statement, progress report and financial status report).
Requests for administrative supplements must be submitted from an authorized official at the recipient organization and include the grant number and name of the Contact PD/PI in the request. For all applications, post-submission information, progress reports, and prior approval Written approval by an authorized HHS official, e.g., a designated IC GMO, evidencing prior consent before a recipient undertakes certain activities or incurs specific costs (see Administrative Requirements-Changes in Project and Budget-Prior Approval Requirements). requests including requests to add or drop a PI, the recipient organization remains responsible for securing and retaining the required written assurance signatures from each identified PD/PI.
A change in Contact PD/PI may be designated in a non-competing continuation progress report; the Contact PD/PI must be a member of the existing leadership team and associated with the recipient organization. Revision of the Leadership Plan during the project period may be accomplished through a joint decision of the PD/PIs and reported in a non-competing continuation progress report.
All existing prior approval Written approval by an authorized HHS official, e.g., a designated IC GMO, evidencing prior consent before a recipient undertakes certain activities or incurs specific costs (see Administrative Requirements-Changes in Project and Budget-Prior Approval Requirements). requirements apply to multiple PD/PI awards, including the change in status of any one of the PD/PIs or the addition of a PD/PI; refer to Administrative Requirements-Prior Approval Requirements in IIA. If a PD/PI withdraws from the grant or is no longer able to work on the project, a revised Leadership Plan or description of the impact on the project of a change to a single PD/PI award must be submitted as part of the prior approval Written approval by an authorized HHS official, e.g., a designated IC GMO, evidencing prior consent before a recipient undertakes certain activities or incurs specific costs (see Administrative Requirements-Changes in Project and Budget-Prior Approval Requirements). request. NIH will evaluate the request considering the project as a whole, including the impact on the scope of work and budget.
If the Contact PD/PI changes institutions, the recipient institution will need to consider options. Since it is required that the Contact PD/PI be affiliated with the recipient institution in the Commons, the institution may choose to designate another PD/PI as the Contact. Another option would be to relinquish the grant and allow it to be transferred. Contact PD/PIs considering transferring should consult with the NIH awarding IC The NIH organizational component responsible for a particular grant program or set of activities. The terms "NIH IC," or "awarding IC" are used throughout this document to designate a point of contact for advice and interpretation of grant requirements and to establish the focal point for requesting necessary prior approvals or changes in the terms and conditions of award. early in the process to discuss options.