10.2.2 Liquidated Damages
Invitations for bids must stipulate a time for completion of the project, expressed either in calendar days or as a fixed date, for each prime contract to be awarded under the project.
At the option of the recipient, a liquidated damages provision may be included in the contract, allowing for assessment of damages when the contractor has not completed the construction by the date specified in the contract. Liquidated damages must be realistic and justified and must be approved by NIH before solicitation. Where damages are assessed, any amounts paid belong to the recipient.